Construction well underway at TRETTI Condos
August 28, 2022

Step by step, floor by floor, and with the unwavering commitment to quality workmanship, innovation and excellence that has become a signature of Collecdev construction, the Scandinavian-inspired lifestyle at TRETTI is coming to life. Here are the latest construction updates from the site:

  • Exterior landscaping is 70% complete, with planters and plants taking root.
  • The building is now fully enclosed - including roofing, window wall, curtain wall and EIFS (the Exterior Insulation Finishing System).
  • The underground parking garage is complete and EV charging stations have been installed.
  • Drywall installation is complete in the amenity spaces on the ground floor and in suites up to the 7th floor.
  • Elevator installation is ongoing, preparing to move residents quickly and efficiently to their front door.
  • Bathroom flooring, wall tile and vanity millwork is complete up to the 6th floor creating the background for the thoughtful and balanced spaces that combine timeless design with a Scandinavian flair.
  • Kitchen millwork has been installed up to the 6th floor, a gourmet space that will inspire your inner chef.
  • First occupancy dates are scheduled for early 2023.

Stay tuned for more exciting updates coming soon as we move on to completing the upper floor amenity spaces and suites at this incredible community.